Struthers Scientific to support Blaw-Knox on butane system contract

Struthers Scientific and International will support the Blaw-Knox review work under a subcontract amounting to approximately half the full contract amount. Through the Struthers subcontract, OSW...

Water Desalination Report, 15-12-1966

OSW plans brackish water freezing plant

Meanwhile, OSW plans for a brackish water freezing plant are requiring more time to firm up. Money included in the current FY 1967 budget for the freezing pilot plant amounts to $350,000. But a...

Water Desalination Report, 15-12-1966

Westinghouse desalting plant sales

The Westinghouse desalting sales record is pointed to with pride by co. president, D.C. Burnhain, who says business was better than expected this year in comparing the firm's total sales of...

Water Desalination Report, 15-12-1966

Cyrus William Rice receives OSW desalting plants

Cyrus William Rice has won a $48,000 contract to design and set up corrosion testing and product water treatment programs at all of OSW's desalting plants. The modest-sized Pittsburgh co, is...

Water Desalination Report, 15-12-1966

California Water Chief resigned

California Water Chief William E. Warne has resigned his office. Warne, principal architect of the desalting agreement signed between Calif, and Dept. of Interior last year (WDR, 25 Mar.'65,2),...

Water Desalination Report, 08-12-1966

Construction invitation issued

OSW's construction invitation for the 17 MGD test module evaporators, with the desalting industry alerted it was coming sometime during November, made it before the month's end last week -- but not...

Water Desalination Report, 08-12-1966

Stronger bond with Russia

Opposition to renewing the desalting technology exchange pact with Russia P is building up from several quarters, and it seems for sure that any possible extension of the agreement will get close...

Water Desalination Report, 08-12-1966

Industry dissent

Dissent to continuing the agreement is now being stirred by industry. Strongest dissenter is Westinghouse, which competed at the recent bid opening in Kuwait for the biggest desalting order ever --...

Water Desalination Report, 08-12-1966

OSW's budget

OSW's budget for fiscal 1968 will tip the scales at $39 million, as a result of final huddles now taking place between the Budget Bureau and OSW's administrative staff, At that amount, it would be...

Water Desalination Report, 08-12-1966

Magic figure mystery

It gets cloudy when attempting to say why the upcoming OSW budget is not up to expanded program levels. In OSW's view there is nothing magical about the $200 million authorized for the stepped-up...

Water Desalination Report, 08-12-1966

Jubail 3a IWP - Saudi Arabia

The client has officially named the ACWA Power-led team as preferred bidder for the contract. Four bids were submitted: 1) ACWA Power/GIC/Al Bawani - SAR1.54861/m3 ($0.41/m3); 2) Marubeni/Marafiq -...

Az-Zour North stage 2/3 IWPP - Kuwait

The client has indicated that there could be a development on advisory tender documents on 5th April 2020, after the process of re-issuing the documents was put on hold as a result of the governmen...

Al Khairan IWPP - Kuwait

The client has indicated that there could be a development on advisory tender documents on 5th April 2020, after the process of re-issuing documents was put on hold as a result of the government sh...

West Basin, CA - U.S.A.

The District plans to hold a "Lunch & Learn" class on 1st May 2020 devoted to water desalination as part of its outreach programme. Interested individuals can sign up here: https://www.westbasin.or...

Skhira SWRO - Tunisia

Compagnie des Phosphates de Gafsa and Tunisia's PPP unit (IGPPP) are working on preparatory studies, and an RFQ for construction is scheduled to be released later in 2020.

NuevaUnión (formerly Relincho Copper Mine) - Chile

Teck Resources announced at the end of February 2020 that the feasibility study for the NuevaUnión project is now expected to be delivered later in Q1 2020.

Facility E IWPP - Qatar

The deadline for bid submissions has been extended to 30 April. Bidding groups are understood to include Engie/Mitsui, Itochu, Kepco/Mitsubishi, Marubeni, PowerChina and Sumitomo. A consultancy tea...

Al Khairan IWPP - Kuwait

The process of reissuing advisory tender documents has been put on hold as a result of the government shutdown in Kuwait. Three advisory consortia passed the technical evaluation stage following th...

Az-Zour North stage 2/3 IWPP - Kuwait

The process of reissuing advisory tender documents has been put on hold as a result of the government shutdown in Kuwait. Three advisory consortia passed the technical evaluation stage following th...

Huntington Beach SWRO, CA - U.S.A.

The Santa Ana Regional Water Quality Control Board has cancelled its 3rd April 2020 meeting, at which it was due to decide whether to finalise the tentative order renewing the project's NPDES permi...

Mahdia (phase 1) - Tunisia

Sonede is running a water resource audit with the World Bank to assess the need for, and capacity of a potential desalination plant. Conclusions are due by May 2020 at the latest, and if the audit ...

Kerkennah - Tunisia

Although the feasibility studies are still underway, Sonede is leaning towards a brackish water desalination plant rather than a seawater desalination plant, because of the technological constraint...

Alger West (Fouka Marine) - Algeria

Due to the COVID-19 outbreak, AEC has postponed the opening of financial bids again until 31 March 2020. Two companies were shortlisted following the evaluation of technical bids, and the lower of ...

Weatherford reuse project, TX - U.S.A.

The client has yet to receive a final permit from TCEQ, and therefore the advertisement for construction bids is now scheduled for summer 2020, beginning with the WWTP improvements, followed by two...

Shuaiba North - Kuwait

The Ministry of Electricity and Water is looking to sell a 205,000m3/d & 778MW desalination and power plant. Two requests for proposals from advisors have been issued by the client. One covers the ...

Bahía de Palma - Spain

On 16 March 2020, the bidders were revealed to be as follows: 1) Global Omnium Medioambiente; 2) FACSA/Tedagua; 3) Sacyr/Cadagua; 4) STS/Aquambiente; 5) Aqualia/Acciona Agua. Economic proposals are...

Valdelentisco - Spain

To operate and maintain the 136,000m3/d seawater reverse osmosis plant at Valdelentisco in Murcia. The economic and technical bid scores are as follows: 1) Abengoa (€7.547 million/6 pts); 2) Accion...

Pure Water Soquel, CA - U.S.A.

Jacobs is understood to be the frontrunner for the O&M contract – which is styled as an "operations and management-at-risk" (OMAR) arrangement.

Post Falls Water Reclamation Facility, ID upgrade - U.S.A.

Construction bids are due in on 14 May 2020.

Morro Bay WWTP, CA - U.S.A.

On 10 March 2020, the EPA announced that it will disburse a $62 million WIFIA loan to support the project, which is estimated to save the City $29 million over the lifetime of the project. Construc...

Huntington Beach SWRO, CA - U.S.A.

The Santa Ana Regional Water Quality Control Board will hold a second workshop on 13 March 2020 to discuss the renewal of the NPDES permit required for the desalination plant to move ahead. The wor...

Antioch BWRO, CA - U.S.A.

Although a progressive design-build delivery method had previously been chosen to implement the project, it will now move forward as a traditional design-bid-build project. Carollo Engineers expect...

Post Falls Water Reclamation Facility, ID upgrade - U.S.A.

Construction bids are expected to be advertised as soon as 13 March 2020.

GWRS Phase III, CA - U.S.A.

The final contract for the GWRS final expansion project is due to be bid out later in March 2020, with a provisional submissions deadline of 26 May 2020. The scope includes the slip-lining of appro...

Palo Alto Reuse, CA - U.S.A.

At its meeting on 2nd March 2020, Palo Alto City Council voted to accept the Northwest County Recycled Water Strategic Plan Report. Meanwhile, an RFP for the design of the 1.125MGD (4,258m3/d) salt...

MWD Regional Recycled Water Scheme, CA (Phase 1) - U.S.A.

The follow-up workshop is now scheduled to be held in June 2020, and will examine financial considerations relating to the full-scale project, in anticipation of further board action.

Pure Water Soquel, CA - U.S.A.

The Black & Veatch/Filanc/Trussell Technologies team has been awarded the progressive design-build contract relating to the AWPF and the addition of tertiary treatment at the Santa Cruz WWTP. Phase...

Malibu Civic Center Phase 2, CA - U.S.A.

The plant expansion requires the formation of an assessment district, and an RFQ/P has been released seeking assessment engineering and district administration services in connection with the phase...

Pure Water Soquel, CA - U.S.A.

A Coastal Commission hearing is due to be held on 11 March 2020 in connection with the District's application for a Coastal Development Permit for the project. Meanwhile, the Black & Veatch/Filanc/...

El Tarf - Algeria

AEC has postponed the opening of financial bids until 17 March 2020. Three companies were shortlisted following the evaluation of technical bids, and the lowest bidder will provisionally be awarded...